At our community meetings, you asked questions for our coastal/structural engineers and for the Chicago Division of the U.S. Army Corps of Engineers (USACE). Here are their responses to your questions. Question. The McLaren Condition Study rates the limestone revetment as pretty good for the Corps' purpose of erosion control. And McLaren's Vulnerability and Alternatives Design reports use the Corps' research to conclude that the revetment needs repair but is safe as is. Has the Corps considered doing nothing and just letting the revetment erode like a natural shoreline? Much like a natural shore on Lake Superior or in Maine? Has the Conservancy considered that alternative? Answer. Brian Moody, McLaren: The intent of our Alternatives Design Study was to restore and preserve the existing, historic fabric of the structure at the Point. Allowing the revetment to continue to fall into disrepair would allow for the continued loss of upland park area, reduce safety for park patrons, and erode the connection and integrity of the historic structure. Repair and maintenance of the limestone block structure are called for. Answer. Mike Padilla, Chicago USACE: The Corps studies always include the “do nothing” alternative. In the case of the 1994 Chicago Shoreline study, that alternative was not selected, probably because it was recognized that the revetment “needs repair” as stated in the question. ### Question. The original Burnham Plan for the lakefront had islands acting as breakwaters to protect the Chicago shoreline. This seems like a very good solution for minimizing wave forces and erosion damage to the City’s lakefront parks and spaces. There are effective breakwaters left at Steelworkers Park. Has the Corps and the City considered breakwaters offshore these South Side parks like Morgan Shoal and the Point? Has the Conservancy considered this alternative? If not, why? Answer. Brian Moody, McLaren: Offshore breakwaters could be an effective option at the Point, although not required. If the Corps and the City decided to build a breakwater, the limestone block waterfront structure would still require repair and rehabilitation as well as maintenance. Answer. Mike Padilla, Chicago USACE: The offshore islands were, indeed, part of the Burnham Plan. However, in the 1994 study, whole islands were not evaluated. Standard “High Crest” rubble mounds were evaluated in Plan II of the study but were not part of the selected plan. Those type of rubble mounds, while being overall smaller than the islands of the Burnham Plan, are very large and were not seen to be cost effective. The team knew by extension that the islands would not be cost effective either. ### Question: If the U.S. Army Corps expects its plan to take 5 years for construction, how long would it take to complete repair and rehabilitation work at the Point? Answer: Brian Moody, McLaren Engineering Group: A lot depends on how you define the start and end of the project. Assuming you’re only talking about the revetment, our plan presented in the Alternatives Design Study, reusing most of the stones in a rebuilt structure, could easily get between five and ten linear feet a day of production completed. (Maybe more, once the work gets rolling.) With 3,050 linear feet around the perimeter of the Point, that could be as quick as 305 working days. (The total linear feet at the Point is 3,150. One hundred linear feet is the concrete ADA ramp at the south most end of the Point at the 57th Street Beach.) So less than one year to complete repair and rehabilitation per our plan if you’re able to work year round. If work must be seasonal, then no more than two seasons. Also, it could be reasonable to perform the work in phases, allowing as much as 80% of the park to be open at any time. ### Question. In your design plans, please add an easy way for folks to enter the water on both the north and south sides of the Point. I know people aren't supposed to swim there, but we all know that many people do and access is limited for those who aren't overly athletic. Answer. Promontory Point Conservancy: People have been swimming at the Point since the 1920s, before it was a park: that’s nearly 100 years of people deep water swimming from the north and south sides of Promontory Point. Lake Michigan continues to be Chicago’s best cooling station. In our Alternatives Design Study, on pages 25-32, we offer Universal Design Access (ADA compliance) upgrades at three locations along the perimeter of the Point. We worked with our coastal and structural engineers McLaren Engineering Group and with Universal Access architect Frank Heitzman on these options. At the south edge of the Point at 56th Street, the City has already put in an ADA ramp. It’s not particularly easy to get to and the slope is steeper than the preferred 1:20” grade but it does provide access now to the limestone promenade on the south side and the concrete at 57th St Beach. We are proposing some upgrades there to make it more useful for access to the promenade and the water. At the east end where the coffin concrete platform is in place, we are proposing multiple options for accessibility with graceful ramps down to the promenade as well as for riser-long tread stairs (stramps) for those with walkers and canes. These ramps/stramps would be provide easy access for wheelchairs but also for strollers and children to the promenade and the water. At the north edge of the limestone revetment, where it connects with the concrete revetment north of the Point, we again are proposing 1:20’, graceful ramps and stramps from the Lakefront trail down to/up from the concrete and limestone revetments. Again, these would be for those in wheelchairs, with canes and walkers, but also strollers and children. The ramps would make it easy for kids, dogs and their families to get down to the shallow swimming area on the north side of the Point. Finally, in the Alternative Design Study, for example pages 8, 18, 22 and 23, show riprap toe scour protection and alternative toe protection of limestone block steps. These recommendations for toe scour protection in the water protect and strengthen the water facing edge of the revetment. The rubble mound restores the original 1937-1939 structure. But, for access into the water, more limestone block steps down into the water at various places might accommodate. Right now, we are working with an illustrator to create visitations and renderings to make dry engineering drawings more comprehensible so stay tuned for these. I am attaching renderings the Conservancy did for its 2003 engineering study of the Point which are still viable options to give you some clues to what we’re talking about. From what we know about the USACE/CDOT plan, access to the water would be prohibited. The concrete revetment would provide ladders into and out of the water but are really for someone who falls in, not for swimmers. ###
Question. What are the advantages and disadvantages of constructing a revetment with limestone versus concrete? Answer. Brian Moody, McLaren: Advantages of limestone
Question. With water levels low, you can hear waves splashing underneath the concrete coffins. Is Promontory Point going to fall into the water? Is it going to wash away? Answer. Brian Moody, McLaren: The coffin structure is massive (approximately 5 feet thick) and spans between rows of continuous timber piles. This reinforced concrete structure exhibits only minor deterioration and is stable even with the voids beneath the platform.We do recommend that these voids be filled. In our Alternatives Design Study, we offer a grout bag solution to fill the erosion cavity beneath the coffin platform. But Promontory Point is not going to fall into the water anytime in the foreseeable future. ### Question. Why did the existing structure fail? Is it the result of poor design, poor maintenance or some other factor? Answer. Brian Moody, McLaren: The structure has not failed. McLaren and Wiss, Janney, Elstner Associates did extensive above water and below water analysis of the existing structure to determine that, in fact, it functions in overall good condition. Deferred maintenance has resulted in some erosion of the subgrade material under the promenade causing the settling of the limestone blocks. And the erosion in the parkland is caused by lack of adequate drainage of water from the blown spray of storm waves. Over time, this erosion of the parkland has not been replaced with new topsoil and grass seed. The revetment and promenade can be economically repaired using current technology and techniques which will increase the resiliency and useful life of the structure. ### Question. Is the settling of the stone structure related to wave action or to compaction? Answer. Brian Moody, McLaren: Where settling of the individual stones is observed on the promenade portion of the structure and at the top of the stepped stones in the parkland, wave activity and stormwater runoff has made its way into the soil, under and behind the stones. As water returns to Lake Michigan, it carries fill material — whether the subgrade material under the promenade blocks or parkland — out slowly over time. This erosion process leads to displacement of the stones. Using filter fabric and properly sized gravel subgrade can allow for water to pass through the soil, under the stones, and back into the lake without causing similar erosion and undermining of the stones. Our Alternatives Design Study recommends use of these materials to stabilize and lengthen the life of the structure. ### Question. Is it possible to build a limestone revetment that will last? Answer. Brian Moody, McLaren: The limestone revetment has lasted nearly 100 years with little or no maintenance. That’s pretty good. Any structure built on the waterfront will require maintenance and upkeep over time. Rebuilding the revetment as described in our Alternatives Design Study will provide a more resilient structure, which can last indefinitely with periodic maintenance. ### Question. Can the limestone revetment be structurally supported without the use of steel sheet pile? Answer. Brian Moody, McLaren: There are several ways to reconstruct the Point that will provide the same look as was provided 86 years ago. The purpose of the piling, whether timber or steel sheet, is to keep the subgrade material in place under the promenade and protect it from wave force scour. With the piling protecting the subgrade material, the block promenade stays stable and interlocks into a strong structure. The Alternatives Design Study explores several options for the water facing edge of the promenade including replacing the timber piling, which is a perfectly good solution when protected, and reinforcing the existing timber crib with concrete. Another alternative in the Study uses steel sheet pile rolled out along the existing crib structure. All of our alternatives maintain the historic fabric of the limestone block revetment and promenade. ### Question. Is there danger of flooding DuSable Lake Shore Drive from overtopping waves at the Point? Climate change would seem to predict bigger waves and bigger storms. Answer. Brian Moody, McLaren: No. There is no evidence that overtopping waves have damaged the Drive or the Point. There is erosion damage from loss of subgrade material beneath the promenade and lack of adequate drainage in the parkland. From the publicly available materials from the Army Corps and CDOT, there is no evidence that these agencies see flooding danger or damage at the Point. Our Coastal Vulnerability Analysis of a repaired limestone block structure shows that the structure meets the USACE and the City’s extreme wave conditions of +6.8 (2020 storm) and a non-historic +7.7 design wave for coastal resilience. Promontory Point Conservancy: It’s hard to predict the effects of climate change at the Point. Right now, water levels are below average and falling due to increased evaporation, possibly caused by warmer winters and less ice coverage. It’s difficult to predict.
0 Comments
On June 5, the Conservancy hosted a Q&A session about McLaren's condition study for preservation agencies, preservation organizations, the Army Corps, City and Chicago Park District. Here is the recording (55 min.
First, it's very important to know that the "locally preferred plan" is NOT the plan locally preferred by the community. As it currently stands, the “locally preferred plan” is demolition of the limestone revetment and new construction of textured concrete with decorative and ornamental limestone blocks in the parkland. This is what the City (CDOT) and the Chicago Park District (CPD) call the "locally preferred plan" and what they currently plan for the Point. We know that's what CDOT and CPD are planning from public information. First, on CDOT’s Shoreline Protection Project webpage, CDOT clearly states what the “locally preferred plan” is and what they mean by preservation: “The preferred design of the revetment is vertical steel sheet piles to replace the damaged wood piles, and concrete steps and promenade to replace the existing stones. This design maintains safe access to the shoreline while preserving its historical and aesthetic value.” (Promontory Point and Morgan Shoal are listed as "Reach 4-step stone revetment reconstruction from 23rd Street to 57th Street alongside Lake Shore Drive” on the same webpage.) Also, through FOIA, the Conservancy obtained CDOT's BRIC FEMA Pre-application, dated September 30, 2020. On page four of the exhibits, CDOT clearly specifies exactly what it means by "a preservation based approach" at Promontory Point: a new revetment of textured concrete with decorative limestone blocks in the parkland. CDOT engineers confirmed the "locally preferred plan" as recently as October 18, 2022 when the Conservancy walked the Point with CPD and CDOT commissioners and senior staff. In the exhibit pages below excerpted from the BRIC FEMA Pre-application, CDOT and SmithGroup (CPD's favored engineering/planning firm) layout the emergency storm erosion crisis project area and illustrate what the "locally preferred plan" looks like for Promontory Point. As you can see, Promontory Point -- where there is no storm damage erosion crisis and no threat to private property, DuSable Lakeshore Drive or human life -- is falsely bundled with Morgan Shoal as one emergency reach. And the color illustration spells out a purported "preservation based approach" of demolition of the historic limestone revetment and replacement with a concrete revetment. Here, like at 57th Street Beach's concrete revetment, limestone blocks are placed in the nearby parkland for decorative and ornamental purposes and do not function as the revetment. Illustration above: CDOT and SmithGroup's caption reads: "Promontory Point is listed on the National Registry of Historic Places. The City is committed to protecting and preserving this cultural asset and taking a preservation-based approach to shoreline protection. The image below is from shoreline protection installed at Diversey Harbor which takes a similar preservation-based approach. The specific design details for rehabilitation of Promontory Point shoreline will be developed as part of [the Morgan Shoal Project]. The City of Chicago, through its partnership with the US Army Corps of Engineers, has successfully built new revetments throughout Chicago including segments from 51st to 54th Street, 43rd to 45th Street, and 33rd to 37th Street." Obviously, the Conservancy, other preservationists and qualified marine engineering firms with preservation experience disagree with this assessment entirely. Map above: Bundling Promontory Point in a single reach with Morgan Shoal and calling it one project allow CDOT and SmithGroup (CPD) to inflate and exaggerate erosion, storm damage conditions at Promontory Point. CDOT and CPD lump Promontory Point into the second phase of work of the Morgan Shoal Project. Construction has already been awarded to SmithGroup and its partners to begin construction at Morgan Shoal. It's not clear whether that contract includes Promontory Point too in the scope of work. Right now, the City and CPD are fully funded for construction of the current "locally preferred plan" of demolition and a new concrete revetment at Promontory Point and Morgan Shoal. On December 15, 2022, the City won 65% federal funding for its "locally preferred plan". With the passage of the Defense appropriations by Congress, the City and CPD received federal funding appropriation to construct the "locally preferred plan": 65% funding for demolition and a new concrete revetment funnels through the Chicago Army Corps, and the City will pay 35% through its November 2020 General Bond Obligation offering which specifically names Morgan Shoal and Promontory Point as capital projects. The Army Corps, the Mayor's Office and CPD snuck this huge federal appropriation in without informing U.S. Congresswoman Robin Kelly in whose district the Point sits and who has persistently requested federal funds for preservation at the Point and without informing Alderman Leslie Hairston.
Based on circumstancial evidence and the agencies' ongoing obfuscations, the Conservancy believes that the Corps, the City and CPD are using the current General Reevaluation Study (GRR) of the Chicago lakefront, including Promontory Point, to back into CPD's SmithGroup study for demolition and a new concrete revetment at the Point. As confirmed by CPD last June, SmithGroup has completed Phase I (condition/assessment study) and Phase II (design/strategic action plan) for Promontory Point. CPD has refused to release these findings to the press, to elected representatives and to the Conservancy. Neither SmithGroup nor the Chicago Corps has any relevant preservation expertise to make a legitimate plan for a preservation approach at Promontory Point. The terminology "locally preferred plan" comes from the U.S. Army Corps of Engineers which must distinquish between its plan (cheap rubble mound) and the plan preferred by its local clients, CPD and CDOT. Hence, the "locally preferred plan". If the CPD and CDOT were sincere about preservation and listening to the wishes of the community, a genuine preservation approach -- such as the Conservancy's preservation marine engineering studies -- could be adopted by the agencies as the "locally preferred plan". To date, neither the Mayor's Office, CPD, CDOT nor the Corps has supported genuine preservation -- repair and restoration -- at the Point. Cost Points: cost comparisons of the "locally preferred plan" and preservation construction11/1/2022 ![]() We recently discovered -- again -- that repair, restoration and rehabilitation of Promontory Point continues to be cost-effective and cheaper than the City's "locally preferred plan". As you may recall, the City's "locally preferred plan" entails demolition of the historic limestone revetment and new construction of concrete and steel. In 2013, the U.S. Army Corps of Engineers' cost estimate for the "locally preferred plan" was $57m. Adjusted for inflation, the cost of the "locally preferred plan" today is: $75m In sharp contrast, preservation of the Point -- repair, restoration and rehabilitation per the Secretary of the Interior Standards for Historic Preservation -- continues to be cheaper than demolition and new construction. The 2002 Cyril Galvin preservation marine engineering report estimated the cost of repair, restoration and rehabilitation at $4.5m. Adjusted for inflation, that's currently $7.53m, 1/10th the cost of the "locally preferred plan". Given the storm damage erosion at the Point since 2002 and after conversation with four marine engineering firms with preservation experience, we estimate the cost of preservation construction and maintenance at 1/5 - 1/2 the cost of the "locally preferred plan" at: $17-29m Right now, the City is pushing a deception Point: demolition of the limestone revetment, new construction of a concrete revetment with limestone blocks on top as decorative and ornamental. Astronomical to build and to maintain, it is an over-engineered solution for $100m when repair, restoration and rehabilitation of the existing limestone revetment is feasible and multiple times cheaper. This is not a preservation-based approach and violates the Secretary of the Interior Standards for Historic Preservation. We don't need a new concrete revetment. We need the existing limestone revetment -- which still functions at 85 years -- fixed. But even if preservation costs as much as the "locally preferred plan" which it doesn't, Promontory Point would be worth it and park equity on the South Side would be served. |
Categories
All
Archives
February 2025
AuthorDebra Hammond is currently an officer of Promontory Point Conservancy. She has always been tall for her age |